Upcoming Events

10/24/2026
Trunk or Treat

View All Events

2026 Incidents
Jan 42
Feb 40
Mar 38
Apr 30
May 39
Jun 44
Jul 47
Aug 36
Sep
Oct
Nov
Dec
Total 316

2025 Incidents
Jan 30
Feb 33
Mar 29
Apr 25
May 28
Jun 31
Jul 44
Aug 33
Sep 31
Oct 20
Nov 46
Dec 32
Total 382

Past Years
2025 382
2024 350
2023 339
2022 305
2021 474
2020 513
2019 528
2018 423
2017 357
2016 355
2015 300

Web Counters
Website Visitors
Since
February 16, 2024
506,588
Visitors Today
Sep 03, 2026
22

New Pumper Update

Print RSS Facebook Twitter RSS

By Chief Joshua Smith
September 2, 2026

Production continues on the department’s new pumper, with significant progress made throughout August. Major milestones during the month included completion of the cab paint, installation of cab interior components, painting and reassembly of the pump house, continued body construction and metal finishing, and completion of the chassis and frame. The apparatus is continuing to take shape as it progresses through the stages construction and assembly.

Attachments:
Attachment Production Report 10AUG2026.pdf  (17,174k)
Attachment Production Report 15AUG2026.pdf  (16,615k)
Attachment Production Report 29AUG2026.pdf  (33,043k)
 

Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
East Allen Township Volunteer Fire Department
5354 Nor Bath Blvd.
Northampton, PA 18067
Emergency Dial 911
Non-Emergency: (610) 262-6700
E-mail: info@eastallenfire.org
Copyright © 2026 Firehouse Solutions (A Service of Technology Reflections, Inc.)